Operational Test
If the scanner is to receive power from an external power supply, test the
scanner before it is connected to the host system.
Keyboard Wedge Scanners:
1. Plug one end of the coil cable into the keyboard connector on the PC.
Then plug the keyboard connector into the other end of the coil cable.
Plug in the external transformer.
2. Check the AC input requirements of the power supply (for special
circumstances only) to make sure the voltage matches the AC outlet.
Connect AC power to the transformer.
3. Listen for a single beep (red LED on) which indicates the scanner is
ready for use.
RS-232, Light Pen, OCIA and 46xx scanners:
1. Plug the scanner’s coil cable into the MCA (Metrologic Connector
Adaptor).
2. Check the AC input requirements of the power supply to make sure the
voltage matches the AC outlet. Plug the power supply into the MCA and
the appropriate AC outlet. (the socket-outlet shall be installed near the
equipment and shall be easily accessible.)
3. Listen for a single beep (red LED on) which indicates the scanner is
ready for use.